Red Chris Mine

Mining Banner

Red Chris Mine

North Coast Energy was Sub Contracted by Progressive Ventures for the Earlyworks Project at Red Chris Mine.

Scope: North Coast Energy was contacted by Progressive Ventures in helping them execute a multi-sized pipeline for the Early Works Project at Red Chris mine. The installation consisted of Benching and installing over 6 km of multi-size pipe lines for the Raw water and Dewatering lines to help in its drilling activities underground. 

The required fields included:

  • Fusion of over 400 HDPE Joints
  • Installation of 6000m of piping
  • Development of multi-pump configuration
  • Organizing and planning for the Benching and building of over 6000m of new routes for the piping
  • Working in extreme elements
  • Working with the Engineering teams to bring the system to an automated and the use of Electrically driven pumps for the use of Greener energy

Project Length: Oct 2021 – Mar 2023

Workforce Size: 7 workers  

Categories
Recent Projects

Vancouver Airport

vancouver airport

Vancouver Airport

North Coast Energy was contacted by Quattro Constructors to help speed up the time constraints of its installations bringing its fuel facility online due to the high demand of fuel requirements that were being trucked into the terminal. We jumped at the chance to work with Quattro Constructors and it paid off. 

Scope: Organizing, Planning, and executing multi-tie point digs within the city of Richmond and inside the airfield at Vancouver International Airport. 

The required fields included:

  • Following Survey plots
  • Extensive Ground Disturbance requirements working around live active piping and electrical within the airfield
  • Tie-in point coordination between multi subs, Equipment, Crane trucks, Welding, and NDT
  • Backfill and Remediation  

Project Length: Aug 2021 – Oct 2021

Workforce Size: 9 workers